Email from Acting Public Works Director Michael Fay
Date: Wed, 17 Sep 2003 08:11:13 -0400
From: "Michael Fay" (MJF@smtp.co.alachua.fl.us)
To: tjw@ufl.edu
Subject: Re: SW 62 Blvd and SW 43rd St.
The tentative schedule for the SW 24th Avenue project from SW 43rd
Street to SW 34th Street is as follows:
1. Design, permitting, and completion of engineering construction plans
by Berryman and Henigar, Inc. is scheduled to be completed by June,
2004.
2. Advertising and bidding for the construction contract will commence
as soon as #1 above is completed in June, 2004 and all of the necessary
right-of-way has been acquired. The award of the construction contract
should be completed by December, 2004.
The payments to Berryman & Henigar, Inc for the engineering design will
be paid out over the period of September, 2003 to July, 2004 as various
phases of the design is completed.
Michael J. Fay
Acting Public Works Director
Assistant Public Works Director/
Transportation and Development
352-374-5245, ext. 218
MJF@smtp.co.alachua.fl.us